Skip to main content

Right Of Way / Way Leave Clearance for various Electrical Power Transmission Line

Width of maximum right of way permitted as per forest conservation act ‘1980 and its subsequent amendment dated 25thOctober, 1992, are as per Table 1.  Researches are being carried out for further optimizing the Right of Way.
Guidelines of forest environmental rules shall be followed to avoid excessive tree cutting i.e. all the trees should be cut from root level in the 3 m corridor below each line conductor / earth wires.  In the balance corridor, trees branches are only to be lopped to attain the specified clearance as per Table 1.
Table 1 – Guidelines for Right of Way as per forest conservations act 1980 and subsequent amendment dated 25thOctober, 1992

Line voltage (kV)

66

110

132

220

400

500 HVDC

765

Row width (Meter)

18

22

27

35

52

52

85

Electrical clearance: Electrical clearance while power lines crossing each other.
In case of power line crossings, minimum clearance between lowest conductor of line and ground wire / top conductor of the other line shall be as per Table 2.
Table 2 – Minimum clearance in mmbetween lines when crossing each other.

Sr. No.

Line voltage (kV)

66

132

220

400

500 HVDC

765

1

66

2440

3050

4580

5490

6790

7940

2

132

3050

3050

4580

5490

6790

7940

3

220

4580

4580

4580

5490

6790

7940

4

400

5490

5490

5490

5490

6790

7940

5

500 HVDC

6790

6790

6790

6790

6790

7940

6

765

7940

7940

7940

7940

7940

7940

Jumpers in the tension tower are properly bolted with the tension clamp and form a parabolic shape in order to achieve adequate clearance from the structure.
Ground clearance:
Normally, at the time of construction, adequate clearance is provided between lowest conductor and ground, but due to delay in charging / commissioning there are chances of dumping / heaping soil, earth and concrete etc. or stacking bricks etc., that may cause reduction in ground clearance.  In such cases the stored materials shall be removed.
Temporary or permanent structures which do not fulfill the requirement of rule no. 80 of IE rules should be removed prior to charging of transmission line.
The various clearances are given in Table 3 are mandatory.  However all the clearance indicated as per approved drawings by Engineering / Design department of the utility, are to be referred.
Ground clearance of lowest conductors at critical points shall be checked at prevalent temperature in the field by any of the prevalent method and the values of ground clearance at these critical points shall be recorded in the prescribed format.
In case of hilly terrain and for building clearance, the side clearance from conductors and jumpers at critical points shall also be checked and recorded for all phases of conductor/ earth wire towards hill/ building side.
Table 3 – Permissible minimum ground clearance for difference voltage level.

Line voltage (kV)

66

110

132

220

400

500 HVDC

765

Minimum ground clearance  (mm)

5500

6100

6100

7000

8840

12500

15500

Clearance for telephone line crossings
The minimum clearances between the conductors of the power line and tale-communication lines are specified in Table 4
Table 4 – Minimum clearance between conductor of power line and telecommunication line.

Line voltage (kV)

66

110

132

220

400

500 HVDC

765

Clearance (mm)

2440

2750

2750

3050

4480

6860

7900

As per regulations for power lie crossings of railway tracks- 1987 and its subsequent amendment dated 26th August, 1988, the minimum clearance between railway track and the bottom most conductor or power line crossing the railway track shall be as per Table 5
Table 5 – Clearance between conductor and ground wire at mid span

Line voltage / clearance (kV)

66

132

220

400

500 HVDC

765

Clearance Above track (mm)

14100

14600

15400

17900

19300

23400

Over Crane (mm)

2000

2500

3500

6000

7250

11500

Clearance between conductor and ground wire at mid span
The vertical clearance between conductors and earth wire shall be checked randomly say in anyone span of all sections and 10% sections of hilly areas from single line diagram of the towers.  These clearance are specified in Table 6
Table 6 Clearance between conductor and ground wire “at mid span” as per clause no. 4.10.2 of CBIP Transmission Line Manual.

Line voltage (kV)

66

132

220

400

500 HVDC

765

Minimum mid span Clearance (mm)

3000

6100

8500

9000

8500

12400

Minimum clearance above rivers/ lacks
In case of accessible frozen rivers/ lacks, the minimum clearance above frozen rivers/ lacks should be equal to he minimum ground clearance given in Table 3.  The minimum clearance of power conductor over the highest flood level in case of rivers shall be as given in Table 7
Table 7 – Minimum clearance between lowest conductor and highest flood level of river

Line voltage / clearance (kV)

66

132

220

400

765

500 HVDC

Minimum Clearance above river or lack or water stretches Non navigable river (from HFL) in mm

3650

4300

5100

6400

13200

10650

Minimum clearance above navigable river (from HFL) in mm

Popular posts from this blog

What is CSD (Controlled Switching Device) in Electrical System

Definitions CSD (Controlled Switching Device): A device that is installed at the relay and control panel to overcome the transient behaviour of voltage and current during switching. This device synchronizes the switching of each pole of the circuit breaker according to the zero crossing of the corresponding phase. This device is also known as a phase synchronizing device, or PSD for short. Requirement When we switch off an online circuit breaker to disconnect an inductive load, we ideally want to interrupt the current of the system at the zero crossing of the current waveform. However, this is practically impossible to achieve. In a normal circuit breaker, the current interruption may occur near the zero crossing point, but not exactly at it. Since the load is inductive, this sudden interruption of current causes a high rate of change of current (di/dt), which results in a high transient voltage in the system. In low or medium voltage power systems, this transient voltage during circui...

Roles and Responsibilities of SLDC- State Load Dispatch Center in India

As per section 33 of Electricity Act – 2003 (Central Act 36 of 2003), SLDC-State Load Dispatch centers performs:- SLDC- State Load Dispatch Center suppose to carry out following functions or Roles and Responsibilities of State Load Dispatch Center. Scheduling: All Open Access users (excluding wind and mini hydel and generating stations having total capacity not less than 5 MW and up to 15 MW opting for injection under UI) that are connected to the Grid shall schedule and dispatch according to instructions given by SLDC. The methodology of scheduling shall be according to provisions of Gujarat State Grid Code and Clauses 26 and 44 of GERC Tariff Regulations. Gaming: SLDC should see that no gaming is done while declaring capacity by generators. Energy Accounting: A State Energy Account, for the billing and settlement of ‘Capacity Charge’, ‘Energy Charge’, ‘UI Charge’ and ‘Reactive Charge’ shall be prepared by the SLDC. The SLDC...