Skip to main content

Overhauling of Electrical Power transformer

Overhauling of transformer is required either due to ageing of transformer or due to fault of transformer & after rectification of fault following steps should be followed for better overhauling.


Draining of complete oil in tank or barrels before draining the oil, the oil in the transformer tank should be heated up by a separate hot oil circulation at around 70’C. So that when the oil is totally drained out, the core & winding assembly will have temperature higher than ambient. This will note be exposed without oil for more than 12 hrs. Before this period either the assembly should be filled with new oil or nitrogen or should be subjected to vacuum. Before draining the oil, the external surface of tank & fittings should be cleaned to locate the point of leakage


Overhauling of OLTC which includes:


Hot oil washing of diverter & selector chamber after untanking diverter switches.


Untanking diverter switches


Cleaning of fixed & moving contacts


Tightening of all the clamping hardware


Replacing all the oil sealing gaskets


Greasing of gears in driving mechanism


Replacement lubricating oil in gear bo


Washing of core coil assembly by hot oil jet to remove sludge carbon Deposition and any other foreign particles deposited over it


Tightening of core studs & checking its IR value


Tightening pressure screws for axial tightness of coil


Attending to any minor abnormalities on core coil assembly


Paper covering to main leads wherever required


Flushing of radiators


Cleaning the tank inside by hot oil jet without untanking core & winding assembly


Preparation & replacement of all the oil sealing gaskets made from rubberised cork sheet confirming to grade RC80C of IS 4253(Part-2) 1960 for whole transformer.


Drying out of core & winding as per procedure laid down as under:


Equalizing diverter chamber of OLTC with main tank, so that the diverter chamber is not subjected to pressure during vaccum.Vaccum pulling by a separate vacuumed  pump up to 700mm or more, provided the tank & cover does not have permanent deflection due to vaccum.For 12 hrs after attending 700mm vaccum.After every vacuum cycle, the quantity of water collected in the condensate of the vacuum system is to be measured & noted for the purpose of knowing the rate of water extracted from the core & winding insulation. The new oil in storage tank is filtered by two stage high vacuum filter machine of minimum 4500LPH capacity & impregnated in transformer tank under vacuum. After oil filling the oil in the transformer tank is filtered to raise the temperature, to 65-70 “C. After raising the temperature, the oil is drained out & dry nitrogen having 99.5% dryness is injected. The nitrogen is kept in the transformer for about 12 to 24 hrs. at least 2/3 cycles to be given.IR value to be measured after each cycle.


Filtration of Oil


After the drying out cycles are over the oil in the transformer is filtered till the BDV & water content values are achieved as required by IS 1866-1983.During this final filtration, a separate degassing column with separate vacuum pump should be used to get better dehydration of oil. During filtration the radiator bank should also be filtered separately or along with filtration should two stage, high vacuums machine of minimum 4500LPH capacity. After filtration the oil will be tested for BDV in presence of GETCO engineer site. The BDV value should meet requirement as per IS 1866-1983.After filtration the oil sample will be tested for water content (PPM) at ERDA. The results should meet requirement as per IS 1866-1983.


Dismantling of all the fittings of the transformer such as HT & LT bushing, conservator, explosion vent, Buchholz relay, radiators, top cover, inspection cover etc. including hiring of crane.

Popular posts from this blog

Right Of Way / Way Leave Clearance for various Electrical Power Transmission Line

Width of maximum right of way permitted as per forest conservation act ‘1980 and its subsequent amendment dated 25 th October, 1992, are as per Table 1.  Researches are being carried out for further optimizing the Right of Way. Guidelines of forest environmental rules shall be followed to avoid excessive tree cutting i.e. all the trees should be cut from root level in the 3 m corridor below each line conductor / earth wires.  In the balance corridor, trees branches are only to be lopped to attain the specified clearance as per Table 1. Table 1  – Guidelines for Right of Way as per forest conservations act 1980 and subsequent amendment dated 25 th October, 1992 Line voltage (kV) 66 110 132 220 400 500 HVDC 765 Row width (Meter) 18 22 27 35 52 52 85 Electrical clearance:   Electrical clearance while power lines crossing each other. In case of power line crossings, minimum clearance between lowest conductor of line and ground wire / top conductor of ...

What is CSD (Controlled Switching Device) in Electrical System

Definitions CSD (Controlled Switching Device): A device that is installed at the relay and control panel to overcome the transient behaviour of voltage and current during switching. This device synchronizes the switching of each pole of the circuit breaker according to the zero crossing of the corresponding phase. This device is also known as a phase synchronizing device, or PSD for short. Requirement When we switch off an online circuit breaker to disconnect an inductive load, we ideally want to interrupt the current of the system at the zero crossing of the current waveform. However, this is practically impossible to achieve. In a normal circuit breaker, the current interruption may occur near the zero crossing point, but not exactly at it. Since the load is inductive, this sudden interruption of current causes a high rate of change of current (di/dt), which results in a high transient voltage in the system. In low or medium voltage power systems, this transient voltage during circui...

Roles and Responsibilities of SLDC- State Load Dispatch Center in India

As per section 33 of Electricity Act – 2003 (Central Act 36 of 2003), SLDC-State Load Dispatch centers performs:- SLDC- State Load Dispatch Center suppose to carry out following functions or Roles and Responsibilities of State Load Dispatch Center. Scheduling: All Open Access users (excluding wind and mini hydel and generating stations having total capacity not less than 5 MW and up to 15 MW opting for injection under UI) that are connected to the Grid shall schedule and dispatch according to instructions given by SLDC. The methodology of scheduling shall be according to provisions of Gujarat State Grid Code and Clauses 26 and 44 of GERC Tariff Regulations. Gaming: SLDC should see that no gaming is done while declaring capacity by generators. Energy Accounting: A State Energy Account, for the billing and settlement of ‘Capacity Charge’, ‘Energy Charge’, ‘UI Charge’ and ‘Reactive Charge’ shall be prepared by the SLDC. The SLDC...