Skip to main content

Remarkable years in electrical power sectors of India | Landmarks

Here are some remarkable years or land mark in electrical power sector of India.

In 1887 First hydro based power plant was commissioned at Darjeeling in electrical power system of India.
In 1890 first steam based power plant was commissioned at Calcutta in electrical power system of India.
In 1955 first 132Kv AC transmission line was commissioned in electrical power system of India.
In 1959 first Nuclear power plant at trombay in electrical power system of India.
In 1961 first 220Kv AC transmission line was commissioned in electrical power system of India.
In 1964 different load dispatch center formed in electrical power system of India.
In 1975 first 400Kv Ac transmission line between Dehar and panipat was commissioned in electrical power system of India.
In 1978 first 500MW, 220Kv Thermal Power station was commissioned at Trombay and first 500 MW, 400Kv nuclear power station was commissioned at Tarapor in electrical power system of India.
In 1978 SF6 and Vacuums circuit breakers introduced in electrical power system of India.
In 1981 Biogas base power projects initiated nationalized in electrical power system of India.
In 1989 First Back to Back HVDC transmission line commissioned at vindyachal in electrical power system of India.
In 1989 Power Grid Corporation of India has been formed.
In 1989 First Gas base power plant formed in electrical Power system of India.
In 1991 First +/- 500Kv DC long transmission line Commissioned in electrical Power system of India.
In 1992 First wind turbine power generator commissioned in electrical power system of India.
In 1996 Generation is made open for private sector in electrical power system of India.
In 1997 Power Sector made open for Private sector in electrical power system of India.
In 2008 First 765Kv Ac transmission line Sipat-Seoni commissioned by Power grid corporation of India.

Popular posts from this blog

Right Of Way / Way Leave Clearance for various Electrical Power Transmission Line

Width of maximum right of way permitted as per forest conservation act ‘1980 and its subsequent amendment dated 25 th October, 1992, are as per Table 1.  Researches are being carried out for further optimizing the Right of Way. Guidelines of forest environmental rules shall be followed to avoid excessive tree cutting i.e. all the trees should be cut from root level in the 3 m corridor below each line conductor / earth wires.  In the balance corridor, trees branches are only to be lopped to attain the specified clearance as per Table 1. Table 1  – Guidelines for Right of Way as per forest conservations act 1980 and subsequent amendment dated 25 th October, 1992 Line voltage (kV) 66 110 132 220 400 500 HVDC 765 Row width (Meter) 18 22 27 35 52 52 85 Electrical clearance:   Electrical clearance while power lines crossing each other. In case of power line crossings, minimum clearance between lowest conductor of line and ground wire / top conductor of ...

What is CSD (Controlled Switching Device) in Electrical System

Definitions CSD (Controlled Switching Device): A device that is installed at the relay and control panel to overcome the transient behaviour of voltage and current during switching. This device synchronizes the switching of each pole of the circuit breaker according to the zero crossing of the corresponding phase. This device is also known as a phase synchronizing device, or PSD for short. Requirement When we switch off an online circuit breaker to disconnect an inductive load, we ideally want to interrupt the current of the system at the zero crossing of the current waveform. However, this is practically impossible to achieve. In a normal circuit breaker, the current interruption may occur near the zero crossing point, but not exactly at it. Since the load is inductive, this sudden interruption of current causes a high rate of change of current (di/dt), which results in a high transient voltage in the system. In low or medium voltage power systems, this transient voltage during circui...

Roles and Responsibilities of SLDC- State Load Dispatch Center in India

As per section 33 of Electricity Act – 2003 (Central Act 36 of 2003), SLDC-State Load Dispatch centers performs:- SLDC- State Load Dispatch Center suppose to carry out following functions or Roles and Responsibilities of State Load Dispatch Center. Scheduling: All Open Access users (excluding wind and mini hydel and generating stations having total capacity not less than 5 MW and up to 15 MW opting for injection under UI) that are connected to the Grid shall schedule and dispatch according to instructions given by SLDC. The methodology of scheduling shall be according to provisions of Gujarat State Grid Code and Clauses 26 and 44 of GERC Tariff Regulations. Gaming: SLDC should see that no gaming is done while declaring capacity by generators. Energy Accounting: A State Energy Account, for the billing and settlement of ‘Capacity Charge’, ‘Energy Charge’, ‘UI Charge’ and ‘Reactive Charge’ shall be prepared by the SLDC. The SLDC...