Skip to main content

Various Testing equipments used for Electrical Installations

At the time of Electrical Installation various Testing equipments used by Electricians according to their need. It can be single function or multifunction equipments.
New Electrical Installation should be tested before its commissioning and charging. Testing equipments should meet certain international accepted standards.
Here we will understand the operation of Various Electrical testing equipments:

 1) Themography Equipment


Electrical equipments generates heat under operating conditions. At the time of Overload and loose connections heat generation is more.
As show in above picture, Different colors shows difference in temperature. So, Ultimately, we will come to know the heating produce by the equipments or at the connections of different parts.

 2) Phase Sequence tester

Phase sequence tester is used to check correct phase rotation of 3-phase supplies. Rotating Lamps or indicators shows phase rotation of 3-ph system at particular measuring point.

3) Low Resistance Tester


This is very useful Testing Instruments used to measure earth resistance or continuity of conductor or any electrical path.
This instrument has voltage below 24 volts and current less than 200 mA. Resistance measuring range from 0.2Ω to 2Ω and with resolution of 0.01Ω.
In old days analogue instruments were used, nowadays digital instruments with self ranging functions are used in Electrical installations.

4) Insulation Resistance meter

Most widely used testing equipment in electrical installations to measure Insulation Resistance of any Electrical Equipments. It shows insulation Resistance between Live phase and earth.
At the time of measurement it should takes 1 mAmp. It is also called high resistance tester because it measures Resistance in Mega-ohms.

5) Earth Fault loop Impedance meter

This instrument is to measure impedance of the whole Earth fault current loop.
Impedance of the whole Fault current loop should be Low enough for operation of over current protective devices to operate withing standard time disconnection time.
At the time of testing low current flow should be there to avoid unwanted tripling of the devices.

6) Earth electrode resistance tester

Measurement of Earth electrode resistance is required particularly sensitive equipment like generators and transformers at time of installation.
During this test equipotential lead should be disconnect from each earth electrode. This tester is always comes with 3 or 4 probes. Measured value of resistance is in terms of ohms.

7) Prospective short circuit current test

Prospective short circuit current test used to measure amount of current that would flow at the time of short circuit of two conductor of live phases. The value of the current is in terms of Kilo Ampere.
Most of the instruments measures current between phase and neutral than doubling of than value gives phase to phase current at the time of electrical installation measurement.

8) Polarity test

At the time of Electrical installation, by engineers this test can be done by Voltmeter or test lamp to ensure that all the switches and circuit breakers are connected in Live conductor.

9) Residual current device tester

This test is done by electrical engineers to verify the effectiveness of residual current devices(RCDs) at the time of operation with correct effectiveness.

Popular posts from this blog

Right Of Way / Way Leave Clearance for various Electrical Power Transmission Line

Width of maximum right of way permitted as per forest conservation act ‘1980 and its subsequent amendment dated 25 th October, 1992, are as per Table 1.  Researches are being carried out for further optimizing the Right of Way. Guidelines of forest environmental rules shall be followed to avoid excessive tree cutting i.e. all the trees should be cut from root level in the 3 m corridor below each line conductor / earth wires.  In the balance corridor, trees branches are only to be lopped to attain the specified clearance as per Table 1. Table 1  – Guidelines for Right of Way as per forest conservations act 1980 and subsequent amendment dated 25 th October, 1992 Line voltage (kV) 66 110 132 220 400 500 HVDC 765 Row width (Meter) 18 22 27 35 52 52 85 Electrical clearance:   Electrical clearance while power lines crossing each other. In case of power line crossings, minimum clearance between lowest conductor of line and ground wire / top conductor of ...

What is CSD (Controlled Switching Device) in Electrical System

Definitions CSD (Controlled Switching Device): A device that is installed at the relay and control panel to overcome the transient behaviour of voltage and current during switching. This device synchronizes the switching of each pole of the circuit breaker according to the zero crossing of the corresponding phase. This device is also known as a phase synchronizing device, or PSD for short. Requirement When we switch off an online circuit breaker to disconnect an inductive load, we ideally want to interrupt the current of the system at the zero crossing of the current waveform. However, this is practically impossible to achieve. In a normal circuit breaker, the current interruption may occur near the zero crossing point, but not exactly at it. Since the load is inductive, this sudden interruption of current causes a high rate of change of current (di/dt), which results in a high transient voltage in the system. In low or medium voltage power systems, this transient voltage during circui...

Roles and Responsibilities of SLDC- State Load Dispatch Center in India

As per section 33 of Electricity Act – 2003 (Central Act 36 of 2003), SLDC-State Load Dispatch centers performs:- SLDC- State Load Dispatch Center suppose to carry out following functions or Roles and Responsibilities of State Load Dispatch Center. Scheduling: All Open Access users (excluding wind and mini hydel and generating stations having total capacity not less than 5 MW and up to 15 MW opting for injection under UI) that are connected to the Grid shall schedule and dispatch according to instructions given by SLDC. The methodology of scheduling shall be according to provisions of Gujarat State Grid Code and Clauses 26 and 44 of GERC Tariff Regulations. Gaming: SLDC should see that no gaming is done while declaring capacity by generators. Energy Accounting: A State Energy Account, for the billing and settlement of ‘Capacity Charge’, ‘Energy Charge’, ‘UI Charge’ and ‘Reactive Charge’ shall be prepared by the SLDC. The SLDC...