Skip to main content

Why Accidents occurs in Electrical System/substation : How to avoid it

The major factors which causes the Accidents are as follows.


Negligence of duty.


Improper Planning of work.


Improper working method.


Lack of knowledge.


Over enthusiasm.


Avoiding procedures laid-down and avoiding safety measures.


Hastiness.


Improper communication.


How to avoid Accidents in Electrical System?


The personal working should take Line Clear Permit (LCP) and should ensure that the portion in which the work is to be done is electrically isolated & earthed.


Operator should put indication plate invariably clearly indicating that      “ Man at Work “.


The In charge of work should ensure that the portion in which work is to be carried out is properly earthed & cordon the work site with boundary in which the man has to work.


The In charge should clearly explain the entire scope of work & the role of each person.


The In charge should ensure that the person working is equipped with required Safety Tools.


The In charge should ensure the proper working condition of tools & tackles.


The In charge should remain present at the place of work where the work is in close vicinity of electrically live portion.


After completion of the job the In charge should ensure that all man and material is removed from the place work and earthing done by him is removed before returning of LCP.


The operator should verify the place of work and then after carry out necessary operation.


In case of shut down on one circuit of D/C transmission line, the In charge should take care that the personal climb on the dead line only.


The man on work on line should earth the portion to double ensure safe condition and to avoid induction effect.


The man on work on line should use safety appliances. In charge of work should ensure the same.


On completion of work, the In charge should take care that all the men has return from line, tools-tackles and earthings are removed from site and then only LCP should be return.


If the work is given on contract basis, the In charge should ensure that the contractor works as per laid-down procedures and observing necessary safety majors.


The work should be carry out as per IE rules and no compromise should be made with IE rules.


In sub-stations every Panel & Bay should be provided with name plate. On transmission line name plate and circuit identification plate should be provided on each tower.


In short the work should be carry out with full concentration, complete knowledge, complete tools-tackles and observing safety majors to avoid an accident.

Popular posts from this blog

Right Of Way / Way Leave Clearance for various Electrical Power Transmission Line

Width of maximum right of way permitted as per forest conservation act ‘1980 and its subsequent amendment dated 25 th October, 1992, are as per Table 1.  Researches are being carried out for further optimizing the Right of Way. Guidelines of forest environmental rules shall be followed to avoid excessive tree cutting i.e. all the trees should be cut from root level in the 3 m corridor below each line conductor / earth wires.  In the balance corridor, trees branches are only to be lopped to attain the specified clearance as per Table 1. Table 1  – Guidelines for Right of Way as per forest conservations act 1980 and subsequent amendment dated 25 th October, 1992 Line voltage (kV) 66 110 132 220 400 500 HVDC 765 Row width (Meter) 18 22 27 35 52 52 85 Electrical clearance:   Electrical clearance while power lines crossing each other. In case of power line crossings, minimum clearance between lowest conductor of line and ground wire / top conductor of ...

What is CSD (Controlled Switching Device) in Electrical System

Definitions CSD (Controlled Switching Device): A device that is installed at the relay and control panel to overcome the transient behaviour of voltage and current during switching. This device synchronizes the switching of each pole of the circuit breaker according to the zero crossing of the corresponding phase. This device is also known as a phase synchronizing device, or PSD for short. Requirement When we switch off an online circuit breaker to disconnect an inductive load, we ideally want to interrupt the current of the system at the zero crossing of the current waveform. However, this is practically impossible to achieve. In a normal circuit breaker, the current interruption may occur near the zero crossing point, but not exactly at it. Since the load is inductive, this sudden interruption of current causes a high rate of change of current (di/dt), which results in a high transient voltage in the system. In low or medium voltage power systems, this transient voltage during circui...

Roles and Responsibilities of SLDC- State Load Dispatch Center in India

As per section 33 of Electricity Act – 2003 (Central Act 36 of 2003), SLDC-State Load Dispatch centers performs:- SLDC- State Load Dispatch Center suppose to carry out following functions or Roles and Responsibilities of State Load Dispatch Center. Scheduling: All Open Access users (excluding wind and mini hydel and generating stations having total capacity not less than 5 MW and up to 15 MW opting for injection under UI) that are connected to the Grid shall schedule and dispatch according to instructions given by SLDC. The methodology of scheduling shall be according to provisions of Gujarat State Grid Code and Clauses 26 and 44 of GERC Tariff Regulations. Gaming: SLDC should see that no gaming is done while declaring capacity by generators. Energy Accounting: A State Energy Account, for the billing and settlement of ‘Capacity Charge’, ‘Energy Charge’, ‘UI Charge’ and ‘Reactive Charge’ shall be prepared by the SLDC. The SLDC...