Skip to main content

Procedure to isolate 400KV Electrical Power Transmission line from system

Following Procedure should be done:-

1) Requisition form for 400Kv Line Clear Permit duly signed by maintenance engineer should be obtained.

2) Ensure that outage of the proposed line is confirmed.

3) Inform opposite end of the 400Kv transmission line and all other concern  before switching OFF breaker.

4) First switch off load end breaker & than Source end breaker of 400Kv Transmission line.

5) Check the Lamp Indication, semaphore for opening of breaker.

6) Check Current transformer relay switching and Potential transformer switching Relay.

7) In Substation Yard just check that all the three poles are opened.

8) Always use Hand gloves for opening and closing Isolator/Earth switch.

9) Open bus & line Isolator from both ends.

10) After confirming opening of isolators at both ends, provide Earthing at both the ends.

11) While providing Local Earthing, Connect Earth wire to the Earthing strip first & then Connect earthing Rod to the Equipment.

12) Ones Bus & Line Isolators open, Earthing provided than Line clear permit of 400Kv Transmission Line can be issue to maintenance engineer.

13) Necessary entries should be made in Line clear permit Book.

14) “Line Clear Permit issued & Mean at work” board should be hanged on the control panel & in Yard.

15) Isolated Bay should be cordoned with the help of Rope for safety measures.

Above mentioned Procedure should be done for Isolating 400KV Electrical Power Transmission line from system.

Popular posts from this blog

Right Of Way / Way Leave Clearance for various Electrical Power Transmission Line

Width of maximum right of way permitted as per forest conservation act ‘1980 and its subsequent amendment dated 25 th October, 1992, are as per Table 1.  Researches are being carried out for further optimizing the Right of Way. Guidelines of forest environmental rules shall be followed to avoid excessive tree cutting i.e. all the trees should be cut from root level in the 3 m corridor below each line conductor / earth wires.  In the balance corridor, trees branches are only to be lopped to attain the specified clearance as per Table 1. Table 1  – Guidelines for Right of Way as per forest conservations act 1980 and subsequent amendment dated 25 th October, 1992 Line voltage (kV) 66 110 132 220 400 500 HVDC 765 Row width (Meter) 18 22 27 35 52 52 85 Electrical clearance:   Electrical clearance while power lines crossing each other. In case of power line crossings, minimum clearance between lowest conductor of line and ground wire / top conductor of ...

What is CSD (Controlled Switching Device) in Electrical System

Definitions CSD (Controlled Switching Device): A device that is installed at the relay and control panel to overcome the transient behaviour of voltage and current during switching. This device synchronizes the switching of each pole of the circuit breaker according to the zero crossing of the corresponding phase. This device is also known as a phase synchronizing device, or PSD for short. Requirement When we switch off an online circuit breaker to disconnect an inductive load, we ideally want to interrupt the current of the system at the zero crossing of the current waveform. However, this is practically impossible to achieve. In a normal circuit breaker, the current interruption may occur near the zero crossing point, but not exactly at it. Since the load is inductive, this sudden interruption of current causes a high rate of change of current (di/dt), which results in a high transient voltage in the system. In low or medium voltage power systems, this transient voltage during circui...

Roles and Responsibilities of SLDC- State Load Dispatch Center in India

As per section 33 of Electricity Act – 2003 (Central Act 36 of 2003), SLDC-State Load Dispatch centers performs:- SLDC- State Load Dispatch Center suppose to carry out following functions or Roles and Responsibilities of State Load Dispatch Center. Scheduling: All Open Access users (excluding wind and mini hydel and generating stations having total capacity not less than 5 MW and up to 15 MW opting for injection under UI) that are connected to the Grid shall schedule and dispatch according to instructions given by SLDC. The methodology of scheduling shall be according to provisions of Gujarat State Grid Code and Clauses 26 and 44 of GERC Tariff Regulations. Gaming: SLDC should see that no gaming is done while declaring capacity by generators. Energy Accounting: A State Energy Account, for the billing and settlement of ‘Capacity Charge’, ‘Energy Charge’, ‘UI Charge’ and ‘Reactive Charge’ shall be prepared by the SLDC. The SLDC...