Skip to main content

Explain transformer losses in short

  1. Core loss : resulting from the alternating core magnetization
  2. Dielectric loss : resulting in insulating material, oil & solid
  3. I²R loss: resulting in the windings
  4. Load ( stray ) loss : largely the result of leakage magnetic field including the eddy currents in the tank walls and conductors
Iron losses:
  • Due to eddy currents and hysterisis
  • Iron losses can be reduced by using superior quality of cold rolled silicon iron sheets
  • No load/core loss/open circuit loss/iron loss is specified at rated voltage
  • Iron loss can be obtained from open circuit tests
Copper loss :
  • I2R loss resulting in the windings
  • Can be reduced by using sufficient cross sections of copper for construction of winding/s
  • Load loss/copper loss/short circuit loss is specified at rated current
  • Copper losses can be obtained from short circuit test without operating the transformer on load
How the hysterisis loss is minimized
  • By using laminated steel sheets of high grade grain oriented steel sheets
  • Laminated surface is subjected to in organic insulation treatment
  • The insulating varnish ensures insulation between the surface
Significance of no load circuit losses( iron losses)
  • The defects in magnetic circuit of the transformer, cause an increase in the no load current and losses
  • Hence, efficiency reduces  and may lead to excessive over heating and reduction in the life span

Popular posts from this blog

Right Of Way / Way Leave Clearance for various Electrical Power Transmission Line

Width of maximum right of way permitted as per forest conservation act ‘1980 and its subsequent amendment dated 25 th October, 1992, are as per Table 1.  Researches are being carried out for further optimizing the Right of Way. Guidelines of forest environmental rules shall be followed to avoid excessive tree cutting i.e. all the trees should be cut from root level in the 3 m corridor below each line conductor / earth wires.  In the balance corridor, trees branches are only to be lopped to attain the specified clearance as per Table 1. Table 1  – Guidelines for Right of Way as per forest conservations act 1980 and subsequent amendment dated 25 th October, 1992 Line voltage (kV) 66 110 132 220 400 500 HVDC 765 Row width (Meter) 18 22 27 35 52 52 85 Electrical clearance:   Electrical clearance while power lines crossing each other. In case of power line crossings, minimum clearance between lowest conductor of line and ground wire / top conductor of ...

What is CSD (Controlled Switching Device) in Electrical System

Definitions CSD (Controlled Switching Device): A device that is installed at the relay and control panel to overcome the transient behaviour of voltage and current during switching. This device synchronizes the switching of each pole of the circuit breaker according to the zero crossing of the corresponding phase. This device is also known as a phase synchronizing device, or PSD for short. Requirement When we switch off an online circuit breaker to disconnect an inductive load, we ideally want to interrupt the current of the system at the zero crossing of the current waveform. However, this is practically impossible to achieve. In a normal circuit breaker, the current interruption may occur near the zero crossing point, but not exactly at it. Since the load is inductive, this sudden interruption of current causes a high rate of change of current (di/dt), which results in a high transient voltage in the system. In low or medium voltage power systems, this transient voltage during circui...

Roles and Responsibilities of SLDC- State Load Dispatch Center in India

As per section 33 of Electricity Act – 2003 (Central Act 36 of 2003), SLDC-State Load Dispatch centers performs:- SLDC- State Load Dispatch Center suppose to carry out following functions or Roles and Responsibilities of State Load Dispatch Center. Scheduling: All Open Access users (excluding wind and mini hydel and generating stations having total capacity not less than 5 MW and up to 15 MW opting for injection under UI) that are connected to the Grid shall schedule and dispatch according to instructions given by SLDC. The methodology of scheduling shall be according to provisions of Gujarat State Grid Code and Clauses 26 and 44 of GERC Tariff Regulations. Gaming: SLDC should see that no gaming is done while declaring capacity by generators. Energy Accounting: A State Energy Account, for the billing and settlement of ‘Capacity Charge’, ‘Energy Charge’, ‘UI Charge’ and ‘Reactive Charge’ shall be prepared by the SLDC. The SLDC...